379. MPS

Master Production Schedule (MPS): the disaggregated version of aggregate planning. Specifies how many of each individual product to make in each week (or shorter bucket).

379.1. What it specifies

For each end-item 𝑖 and time bucket 𝑡 (typically weekly for 6–12 weeks ahead):

379.2. Time-phased records

A typical MPS row for product 𝑖:

Week1234567
Forecast100120110100130120110
Customer orders80954010000
Projected on-hand50507012070100100
MPS quantity10012013015080150110
ATP20259014080150110

ATP at week 𝑡 = production scheduled for that week minus already-committed customer orders.

379.3. How MPS relates to aggregate plan

The aggregate plan says “produce 𝑋 units total in October.” The MPS distributes 𝑋 across:

Constraint: 𝑖MPS𝑖,𝑡 capacity granted by aggregate plan for period containing 𝑡.

379.4. Frozen / liquid / planning zones

The MPS is typically divided into three horizons:

Frozen-zone duration matches production lead time — once you’ve started making it, you can’t easily change.

379.5. MPS feasibility: Rough-Cut Capacity Planning (RCCP)

Before committing to an MPS, check that capacity (workforce, machines, materials) is sufficient. See RCCP.

379.6. Feeding MRP

The MPS is the input to MRP, which explodes each MPS quantity into component requirements via the bill of materials.

379.7. Common pitfalls

379.8. See also