376. MPS

Master Production Schedule (MPS): the disaggregated version of aggregate planning. Specifies how many of each individual product to make in each week (or shorter bucket).

376.1. What it specifies

For each end-item and time bucket (typically weekly for 6–12 weeks ahead):

376.2. Time-phased records

A typical MPS row for product :

Week 1 2 3 4 5 6 7
Forecast 100 120 110 100 130 120 110
Customer orders 80 95 40 10 0 0 0
Projected on-hand 50 50 70 120 70 100 100
MPS quantity 100 120 130 150 80 150 110
ATP 20 25 90 140 80 150 110

ATP at week = production scheduled for that week minus already-committed customer orders.

376.3. How MPS relates to aggregate plan

The aggregate plan says “produce units total in October.” The MPS distributes across:

Constraint: capacity granted by aggregate plan for period containing .

376.4. Frozen / liquid / planning zones

The MPS is typically divided into three horizons:

Frozen-zone duration matches production lead time — once you’ve started making it, you can’t easily change.

376.5. MPS feasibility: Rough-Cut Capacity Planning (RCCP)

Before committing to an MPS, check that capacity (workforce, machines, materials) is sufficient. See RCCP.

376.6. Feeding MRP

The MPS is the input to MRP, which explodes each MPS quantity into component requirements via the bill of materials.

376.7. Common pitfalls

376.8. See also