388. Takt Time

The pace of production needed to match customer demand. From German Takt (beat, rhythm).

If customers want 80 units in an 8-hour shift, the line must produce one unit every minutes.

388.1. Why takt time matters

Takt is the target cycle time for each station and the line overall:

In lean manufacturing, every station is designed to complete its work in less than or equal to the takt time, with engineered slack absorbed by Heijunka boxes / standard WIP.

388.2. Calculating takt

Available time: net production time available, after deducting:

Customer demand: actual delivery requirement, including:

388.3. Worked example

Factory:

So each station must complete its task in 4.2 minutes or less. The overall line cadence is one unit out every 4.2 minutes.

388.4. Takt time vs cycle time

Goal: . When equality holds, line runs perfectly to demand — no over- or under-production.

388.5. Takt time vs throughput

Takt time time between units leaving the line
Throughput units per unit time =

Inverses. Both convey same information.

388.6. Heijunka — level loading

Demand is rarely flat — peaks Monday, valleys Friday, etc. Heijunka (here) smooths production by aggregating demand and producing in a level cadence. Takt is then calculated from average demand, not peak.

388.7. Limitations

388.8. See also