391. Takt Time

The pace of production needed to match customer demand. From German Takt (beat, rhythm).

Takt time=available production timecustomer demand

If customers want 80 units in an 8-hour shift, the line must produce one unit every 48080=6 minutes.

391.1. Why takt time matters

Takt is the target cycle time for each station and the line overall:

In lean manufacturing, every station is designed to complete its work in less than or equal to the takt time, with engineered slack absorbed by Heijunka boxes / standard WIP.

391.2. Calculating takt

Available time: net production time available, after deducting:

Customer demand: actual delivery requirement, including:

391.3. Worked example

Factory:

Takt time=840200=4.2minutes per unit

So each station must complete its task in 4.2 minutes or less. The overall line cadence is one unit out every 4.2 minutes.

391.4. Takt time vs cycle time

Goal: cycle timetakt time. When equality holds, line runs perfectly to demand — no over- or under-production.

391.5. Takt time vs throughput

Takt timetime between units leaving the line
Throughputunits per unit time = 1takt

Inverses. Both convey same information.

391.6. Heijunka — level loading

Demand is rarely flat — peaks Monday, valleys Friday, etc. Heijunka (here) smooths production by aggregating demand and producing in a level cadence. Takt is then calculated from average demand, not peak.

391.7. Limitations

391.8. See also